RH OVE Ecosystem - Detailed Project Timeline

Project Overview

This document provides detailed timelines, milestones, and dependencies for the three sub-projects within the RH OVE Ecosystem implementation.

Project Duration: 12-18 months
Start Date: TBD
Target Completion: TBD


Timeline Summary

Sub-Project Duration Dependencies Key Deliverables
RH OVE Infrastructure 6-8 months None (Foundation) Multi-cluster platform, ADRs, Operations runbooks
Use-Cases Implementation 8-10 months Infrastructure 70% complete Working use-cases, Integration patterns
Migration from VMware 10-12 months Infrastructure 80% complete Migrated workloads, Decommissioned legacy

Project Timeline Visualization

gantt
    title RH OVE Ecosystem Project Timeline
    dateFormat YYYY-MM-DD
    axisFormat %m/%d

    section Infrastructure Project
    Study Phase           :inf-study, 2024-01-01, 28d
    Design Phase          :inf-design, after inf-study, 56d
    Implementation Phase  :inf-impl, after inf-design, 56d
    Testing Phase         :inf-test, after inf-impl, 28d
    Day-2 Operations      :inf-ops, after inf-test, 28d

    section Use-Cases Project  
    Study Phase           :uc-study, after inf-design, 28d
    Design Phase          :uc-design, after uc-study, 56d
    Implementation Phase  :uc-impl, after inf-impl, 84d
    Testing Phase         :uc-test, after uc-impl, 28d
    Day-2 Operations      :uc-ops, after uc-test, 28d

    section Migration Project
    Study Phase           :mig-study, after inf-impl, 56d
    Design Phase          :mig-design, after mig-study, 56d
    Implementation Phase  :mig-impl, after inf-test, 98d
    Testing Phase         :mig-test, after mig-impl, 28d
    Day-2 Operations      :mig-ops, after mig-test, 42d

Timeline Dependencies Diagram

flowchart TD
    A[Project Start] --> B[Infrastructure Study]
    B --> C[Infrastructure Design]
    C --> D[Infrastructure Implementation]
    D --> E[Infrastructure Testing]
    E --> F[Infrastructure Day-2 Ops]

    C --> G[Use-Cases Study]
    G --> H[Use-Cases Design]
    D --> I[Use-Cases Implementation]
    I --> J[Use-Cases Testing]
    J --> K[Use-Cases Day-2 Ops]

    D --> L[Migration Study]
    L --> M[Migration Design]
    E --> N[Migration Implementation]
    N --> O[Migration Testing]
    O --> P[Migration Day-2 Ops]

    F --> Q[Project Complete]
    K --> Q
    P --> Q

    classDef infrastructure fill:#e1f5fe
    classDef usecases fill:#f3e5f5
    classDef migration fill:#e8f5e8
    classDef milestone fill:#fff3e0

    class B,C,D,E,F infrastructure
    class G,H,I,J,K usecases
    class L,M,N,O,P migration
    class A,Q milestone

Resource Allocation Timeline

gantt
    title Detailed Resource Allocation by Phase
    dateFormat YYYY-MM-DD
    axisFormat %m/%d

    section Infrastructure Team
    Infrastructure Architect       :inf-arch, 2024-01-01, 84d
    Infrastructure Architect PT    :inf-arch-pt, 2024-03-25, 28d
    DevOps Engineers (2)           :inf-devops, 2024-01-29, 140d
    System Administrators (2)      :inf-sysadmin, 2024-03-25, 112d
    Security Engineer              :inf-security, 2024-01-29, 84d
    Network Engineer               :inf-network, 2024-01-01, 140d

    section Use-Cases Team
    Solution Architect             :uc-arch, 2024-03-25, 84d
    Application Developers (3)     :uc-dev, 2024-04-22, 140d
    Testing Specialist             :uc-test, 2024-08-12, 56d
    DevOps Engineer                :uc-devops, 2024-05-20, 168d
    Security Specialist            :uc-security, 2024-04-22, 112d
    Business Analyst               :uc-ba, 2024-03-25, 56d

    section Migration Team
    Migration Specialist           :mig-specialist, 2024-04-22, 308d
    VMware Administrators (2)      :mig-vmware, 2024-04-22, 196d
    RH OVE Engineers (2)           :mig-rhove, 2024-08-12, 196d
    Application Owners (2)         :mig-appowner, 2024-07-15, 182d
    Performance Engineer           :mig-perf, 2024-06-17, 210d
    Backup Administrator           :mig-backup, 2024-05-20, 280d

    section Critical Milestones
    Infrastructure 70% Complete   :milestone, 2024-06-17, 1d
    Infrastructure 80% Complete   :milestone, 2024-07-08, 1d
    All Projects Complete         :milestone, 2025-02-24, 1d

Resource Allocation Notes

Infrastructure Team Variable Allocation: - Infrastructure Architect: Full-time during Study/Design phases, part-time for consulting during implementation - DevOps Engineers: Start during Design phase, continue through implementation and operations - System Administrators: Join during Implementation phase, continue for Day-2 operations - Security Engineer: Active during Design through Testing phases - Network Engineer: Active from Study through Implementation phases

Use-Cases Team Variable Allocation: - Solution Architect: Active during Study and Design phases primarily - Application Developers: Core implementation team, active longest duration - Testing Specialist: Primarily active during Testing phase with some overlap - DevOps Engineer: Active during Implementation and operations phases - Security Specialist: Active during Design, Implementation, and Testing phases - Business Analyst: Active during Study and early Design phases

Migration Team Variable Allocation: - Migration Specialist: Project-long involvement for strategy and coordination - VMware Administrators: Active during Study through early Implementation - RH OVE Engineers: Active during Implementation through Day-2 operations - Application Owners: Active during Design, Implementation, and Testing phases - Performance Engineer: Active during Testing and early Implementation phases - Backup Administrator: Active during Implementation through Day-2 operations


Sub-Project 1: RH OVE Infrastructure Project

Phase 1: Study Phase (Weeks 1-4)

Duration: 4 weeks
Effort: 3-4 FTEs

Milestones

  • Week 2: Current state assessment completed
  • Week 3: Gap analysis finalized
  • Week 4: Requirements gathering complete

Deliverables

  • Current infrastructure assessment report
  • Gap analysis document
  • Technical requirements specification
  • Resource capacity planning

Key Activities

  • Analyze existing infrastructure components
  • Document current network, storage, and compute resources
  • Identify skill gaps and training needs
  • Define non-functional requirements (performance, security, scalability)

Phase 2: Design Phase (Weeks 5-12)

Duration: 8 weeks
Effort: 4-5 FTEs

Milestones

  • Week 7: High-Level Design (HLD) approved
  • Week 10: Low-Level Design (LLD) completed
  • Week 12: ADRs finalized and approved

Deliverables

  • High-Level Design document
  • Low-Level Design document
  • 8 Architecture Decision Records (ADRs)
  • Security architecture design
  • Network topology design

Key Activities

  • Design multi-cluster architecture
  • Define GitOps workflows with ArgoCD
  • Plan Cilium CNI implementation
  • Design backup and monitoring strategies
  • Create security and IAM frameworks

Phase 3: Implementation Phase (Weeks 13-20)

Duration: 8 weeks
Effort: 5-6 FTEs

Milestones

  • Week 15: Management cluster deployed
  • Week 17: First workload cluster operational
  • Week 19: GitOps pipeline functional
  • Week 20: Monitoring and backup systems active

Deliverables

  • Deployed multi-cluster RH OVE environment
  • GitOps configuration and workflows
  • Monitoring stack (Prometheus, Grafana, Dynatrace)
  • Backup solution (Rubrik integration)
  • Admission controllers configuration

Key Activities

  • Deploy management and workload clusters
  • Configure Cilium CNI and network policies
  • Implement GitOps with ArgoCD
  • Set up monitoring and alerting
  • Configure backup and disaster recovery

Phase 4: Testing Phase (Weeks 21-24)

Duration: 4 weeks
Effort: 4-5 FTEs

Milestones

  • Week 22: Security testing completed
  • Week 23: Performance benchmarks established
  • Week 24: Infrastructure acceptance testing passed

Deliverables

  • Security assessment report
  • Performance benchmark results
  • Test execution reports
  • Infrastructure acceptance criteria validation

Key Activities

  • Conduct security penetration testing
  • Perform load and stress testing
  • Validate disaster recovery procedures
  • Execute acceptance test scenarios

Phase 5: Day-2 Operations (Weeks 25-28)

Duration: 4 weeks
Effort: 3-4 FTEs

Milestones

  • Week 26: Operations runbooks completed
  • Week 27: Team training finished
  • Week 28: Operations handover complete

Deliverables

  • Day-2 operations runbooks
  • Troubleshooting guides
  • Performance tuning procedures
  • Team training materials

Sub-Project 2: Use-Cases Implementation Project

Phase 1: Study Phase (Weeks 15-18)

Duration: 4 weeks
Effort: 2-3 FTEs
Dependency: Infrastructure Design Phase 75% complete

Milestones

  • Week 16: Use-case requirements gathered
  • Week 17: Business value assessment completed
  • Week 18: Use-case prioritization finalized

Deliverables

  • Use-case requirements specification
  • Business value assessment
  • Implementation priority matrix
  • Resource allocation plan

Phase 2: Design Phase (Weeks 19-26)

Duration: 8 weeks
Effort: 3-4 FTEs

Milestones

  • Week 21: VM lifecycle use-cases designed
  • Week 23: Application deployment patterns defined
  • Week 25: Enterprise integration patterns completed
  • Week 26: All use-case designs approved

Deliverables

  • Use-case HLD and LLD documents
  • Integration architecture designs
  • Security and compliance frameworks
  • Performance and scalability specifications

Phase 3: Implementation Phase (Weeks 27-38)

Duration: 12 weeks
Effort: 4-6 FTEs
Dependency: Infrastructure Implementation 80% complete

Milestones

  • Week 29: VM lifecycle use-cases implemented
  • Week 32: Hybrid applications deployed
  • Week 35: Database services operational
  • Week 37: Security and observability complete
  • Week 38: All use-cases integrated

Deliverables

  • Implemented use-cases with working demonstrations
  • Configuration manifests and scripts
  • Integration patterns and templates
  • Security controls and policies

Phase 4: Testing Phase (Weeks 39-42)

Duration: 4 weeks
Effort: 3-4 FTEs

Milestones

  • Week 40: Functional testing completed
  • Week 41: Integration testing finished
  • Week 42: Business validation approved

Deliverables

  • Test execution reports
  • Performance validation results
  • Business outcome measurements
  • User acceptance documentation

Phase 5: Day-2 Operations (Weeks 43-46)

Duration: 4 weeks
Effort: 2-3 FTEs

Milestones

  • Week 44: Use-case runbooks completed
  • Week 45: Monitoring dashboards operational
  • Week 46: Knowledge transfer complete

Deliverables

  • Use-case operational runbooks
  • Monitoring and alerting configurations
  • Best practices documentation
  • Training materials

Sub-Project 3: Migration Workload from VMware Project

Phase 1: Study Phase (Weeks 21-28)

Duration: 8 weeks
Effort: 3-4 FTEs
Dependency: Infrastructure Implementation 60% complete

Milestones

  • Week 23: VMware inventory completed
  • Week 25: Workload assessment finished
  • Week 27: Migration strategy approved
  • Week 28: Migration waves defined

Deliverables

  • Complete VMware workload inventory
  • Workload assessment and compatibility analysis
  • Migration strategy document
  • Migration wave planning
  • Risk assessment and mitigation plan

Phase 2: Design Phase (Weeks 29-36)

Duration: 8 weeks
Effort: 4-5 FTEs

Milestones

  • Week 31: Migration architecture designed
  • Week 33: VM templates standardized
  • Week 35: Migration procedures documented
  • Week 36: Pilot migration plan approved

Deliverables

  • Migration architecture design
  • VM template standards and configurations
  • Migration procedure documentation
  • Rollback and recovery procedures
  • Pilot migration plan

Phase 3: Implementation Phase (Weeks 37-50)

Duration: 14 weeks
Effort: 5-7 FTEs
Dependency: Infrastructure Testing 100% complete

Milestones

  • Week 39: Pilot migration completed
  • Week 42: Wave 1 migrations finished
  • Week 46: Wave 2 migrations completed
  • Week 49: Wave 3 migrations finished
  • Week 50: All critical workloads migrated

Deliverables

  • Migrated virtual machines and applications
  • Updated VM templates and configurations
  • Migration execution reports
  • Performance optimization results
  • Updated network and security configurations

Phase 4: Testing Phase (Weeks 51-54)

Duration: 4 weeks
Effort: 4-5 FTEs

Milestones

  • Week 52: Application functionality validated
  • Week 53: Performance benchmarks achieved
  • Week 54: Business continuity confirmed

Deliverables

  • Application validation reports
  • Performance comparison analysis
  • Business continuity test results
  • User acceptance confirmation

Phase 5: Day-2 Operations (Weeks 55-60)

Duration: 6 weeks
Effort: 3-4 FTEs

Milestones

  • Week 57: Migration runbooks completed
  • Week 58: Legacy decommissioning planned
  • Week 60: Operations transition complete

Deliverables

  • Migration operations runbooks
  • Legacy infrastructure decommissioning plan
  • Post-migration monitoring procedures
  • Lessons learned documentation

Resource Planning

Team Composition by Sub-Project

Infrastructure Project

  • Infrastructure Architect: 1 FTE
  • DevOps Engineers: 2 FTEs
  • System Administrators: 2 FTEs
  • Security Engineer: 1 FTE
  • Network Engineer: 1 FTE

Use-Cases Implementation

  • Solution Architect: 1 FTE
  • Application Developers: 3 FTEs
  • Testing Specialist: 1 FTE
  • DevOps Engineer: 1 FTE
  • Security Specialist: 1 FTE
  • Business Analyst: 1 FTE

Migration Project

  • Migration Specialist: 1 FTE
  • VMware Administrators: 2 FTEs
  • RH OVE Engineers: 2 FTEs
  • Application Owners: 2 FTEs
  • Performance Engineer: 1 FTE
  • Backup Administrator: 1 FTE

Cross-Project Coordination

Weekly Sync Meetings

  • Architecture review board
  • Technical coordination committee
  • Risk and issue management
  • Resource allocation review

Monthly Steering Committee

  • Progress against milestones
  • Budget and resource adjustments
  • Risk escalation and mitigation
  • Stakeholder communication

Risk Management

High-Risk Areas

  1. Resource Availability: Specialized skills in RH OVE and VMware
  2. Technical Complexity: Multi-cluster networking and storage
  3. Business Continuity: Migration impact on critical workloads
  4. Timeline Dependencies: Sequential phases with limited parallel execution

Mitigation Strategies

  1. Cross-training: Develop skills across multiple team members
  2. Proof of Concepts: Validate technical approaches early
  3. Phased Migration: Minimize business impact through careful wave planning
  4. Buffer Time: Include 15-20% contingency in timeline estimates

Success Metrics

Infrastructure Project

  • 99.9% infrastructure uptime SLA
  • Security compliance audit pass rate: 100%
  • Performance benchmarks met or exceeded
  • Team satisfaction with operational procedures

Use-Cases Project

  • All documented use-cases successfully demonstrated
  • Business value metrics achieved
  • User adoption rates meet targets
  • Documentation completeness and accuracy

Migration Project

  • 100% critical workload migration success
  • Performance parity or improvement: 95% of workloads
  • Business continuity maintained throughout migration
  • Legacy infrastructure decommissioning completed on schedule