RH OVE Ecosystem - Detailed Project Timeline¶
Project Overview¶
This document provides detailed timelines, milestones, and dependencies for the three sub-projects within the RH OVE Ecosystem implementation.
Project Duration: 12-18 months
Start Date: TBD
Target Completion: TBD
Timeline Summary¶
Sub-Project | Duration | Dependencies | Key Deliverables |
---|---|---|---|
RH OVE Infrastructure | 6-8 months | None (Foundation) | Multi-cluster platform, ADRs, Operations runbooks |
Use-Cases Implementation | 8-10 months | Infrastructure 70% complete | Working use-cases, Integration patterns |
Migration from VMware | 10-12 months | Infrastructure 80% complete | Migrated workloads, Decommissioned legacy |
Project Timeline Visualization¶
gantt
title RH OVE Ecosystem Project Timeline
dateFormat YYYY-MM-DD
axisFormat %m/%d
section Infrastructure Project
Study Phase :inf-study, 2024-01-01, 28d
Design Phase :inf-design, after inf-study, 56d
Implementation Phase :inf-impl, after inf-design, 56d
Testing Phase :inf-test, after inf-impl, 28d
Day-2 Operations :inf-ops, after inf-test, 28d
section Use-Cases Project
Study Phase :uc-study, after inf-design, 28d
Design Phase :uc-design, after uc-study, 56d
Implementation Phase :uc-impl, after inf-impl, 84d
Testing Phase :uc-test, after uc-impl, 28d
Day-2 Operations :uc-ops, after uc-test, 28d
section Migration Project
Study Phase :mig-study, after inf-impl, 56d
Design Phase :mig-design, after mig-study, 56d
Implementation Phase :mig-impl, after inf-test, 98d
Testing Phase :mig-test, after mig-impl, 28d
Day-2 Operations :mig-ops, after mig-test, 42d
Timeline Dependencies Diagram¶
flowchart TD
A[Project Start] --> B[Infrastructure Study]
B --> C[Infrastructure Design]
C --> D[Infrastructure Implementation]
D --> E[Infrastructure Testing]
E --> F[Infrastructure Day-2 Ops]
C --> G[Use-Cases Study]
G --> H[Use-Cases Design]
D --> I[Use-Cases Implementation]
I --> J[Use-Cases Testing]
J --> K[Use-Cases Day-2 Ops]
D --> L[Migration Study]
L --> M[Migration Design]
E --> N[Migration Implementation]
N --> O[Migration Testing]
O --> P[Migration Day-2 Ops]
F --> Q[Project Complete]
K --> Q
P --> Q
classDef infrastructure fill:#e1f5fe
classDef usecases fill:#f3e5f5
classDef migration fill:#e8f5e8
classDef milestone fill:#fff3e0
class B,C,D,E,F infrastructure
class G,H,I,J,K usecases
class L,M,N,O,P migration
class A,Q milestone
Resource Allocation Timeline¶
gantt
title Detailed Resource Allocation by Phase
dateFormat YYYY-MM-DD
axisFormat %m/%d
section Infrastructure Team
Infrastructure Architect :inf-arch, 2024-01-01, 84d
Infrastructure Architect PT :inf-arch-pt, 2024-03-25, 28d
DevOps Engineers (2) :inf-devops, 2024-01-29, 140d
System Administrators (2) :inf-sysadmin, 2024-03-25, 112d
Security Engineer :inf-security, 2024-01-29, 84d
Network Engineer :inf-network, 2024-01-01, 140d
section Use-Cases Team
Solution Architect :uc-arch, 2024-03-25, 84d
Application Developers (3) :uc-dev, 2024-04-22, 140d
Testing Specialist :uc-test, 2024-08-12, 56d
DevOps Engineer :uc-devops, 2024-05-20, 168d
Security Specialist :uc-security, 2024-04-22, 112d
Business Analyst :uc-ba, 2024-03-25, 56d
section Migration Team
Migration Specialist :mig-specialist, 2024-04-22, 308d
VMware Administrators (2) :mig-vmware, 2024-04-22, 196d
RH OVE Engineers (2) :mig-rhove, 2024-08-12, 196d
Application Owners (2) :mig-appowner, 2024-07-15, 182d
Performance Engineer :mig-perf, 2024-06-17, 210d
Backup Administrator :mig-backup, 2024-05-20, 280d
section Critical Milestones
Infrastructure 70% Complete :milestone, 2024-06-17, 1d
Infrastructure 80% Complete :milestone, 2024-07-08, 1d
All Projects Complete :milestone, 2025-02-24, 1d
Resource Allocation Notes¶
Infrastructure Team Variable Allocation: - Infrastructure Architect: Full-time during Study/Design phases, part-time for consulting during implementation - DevOps Engineers: Start during Design phase, continue through implementation and operations - System Administrators: Join during Implementation phase, continue for Day-2 operations - Security Engineer: Active during Design through Testing phases - Network Engineer: Active from Study through Implementation phases
Use-Cases Team Variable Allocation: - Solution Architect: Active during Study and Design phases primarily - Application Developers: Core implementation team, active longest duration - Testing Specialist: Primarily active during Testing phase with some overlap - DevOps Engineer: Active during Implementation and operations phases - Security Specialist: Active during Design, Implementation, and Testing phases - Business Analyst: Active during Study and early Design phases
Migration Team Variable Allocation: - Migration Specialist: Project-long involvement for strategy and coordination - VMware Administrators: Active during Study through early Implementation - RH OVE Engineers: Active during Implementation through Day-2 operations - Application Owners: Active during Design, Implementation, and Testing phases - Performance Engineer: Active during Testing and early Implementation phases - Backup Administrator: Active during Implementation through Day-2 operations
Sub-Project 1: RH OVE Infrastructure Project¶
Phase 1: Study Phase (Weeks 1-4)¶
Duration: 4 weeks
Effort: 3-4 FTEs
Milestones¶
- Week 2: Current state assessment completed
- Week 3: Gap analysis finalized
- Week 4: Requirements gathering complete
Deliverables¶
- Current infrastructure assessment report
- Gap analysis document
- Technical requirements specification
- Resource capacity planning
Key Activities¶
- Analyze existing infrastructure components
- Document current network, storage, and compute resources
- Identify skill gaps and training needs
- Define non-functional requirements (performance, security, scalability)
Phase 2: Design Phase (Weeks 5-12)¶
Duration: 8 weeks
Effort: 4-5 FTEs
Milestones¶
- Week 7: High-Level Design (HLD) approved
- Week 10: Low-Level Design (LLD) completed
- Week 12: ADRs finalized and approved
Deliverables¶
- High-Level Design document
- Low-Level Design document
- 8 Architecture Decision Records (ADRs)
- Security architecture design
- Network topology design
Key Activities¶
- Design multi-cluster architecture
- Define GitOps workflows with ArgoCD
- Plan Cilium CNI implementation
- Design backup and monitoring strategies
- Create security and IAM frameworks
Phase 3: Implementation Phase (Weeks 13-20)¶
Duration: 8 weeks
Effort: 5-6 FTEs
Milestones¶
- Week 15: Management cluster deployed
- Week 17: First workload cluster operational
- Week 19: GitOps pipeline functional
- Week 20: Monitoring and backup systems active
Deliverables¶
- Deployed multi-cluster RH OVE environment
- GitOps configuration and workflows
- Monitoring stack (Prometheus, Grafana, Dynatrace)
- Backup solution (Rubrik integration)
- Admission controllers configuration
Key Activities¶
- Deploy management and workload clusters
- Configure Cilium CNI and network policies
- Implement GitOps with ArgoCD
- Set up monitoring and alerting
- Configure backup and disaster recovery
Phase 4: Testing Phase (Weeks 21-24)¶
Duration: 4 weeks
Effort: 4-5 FTEs
Milestones¶
- Week 22: Security testing completed
- Week 23: Performance benchmarks established
- Week 24: Infrastructure acceptance testing passed
Deliverables¶
- Security assessment report
- Performance benchmark results
- Test execution reports
- Infrastructure acceptance criteria validation
Key Activities¶
- Conduct security penetration testing
- Perform load and stress testing
- Validate disaster recovery procedures
- Execute acceptance test scenarios
Phase 5: Day-2 Operations (Weeks 25-28)¶
Duration: 4 weeks
Effort: 3-4 FTEs
Milestones¶
- Week 26: Operations runbooks completed
- Week 27: Team training finished
- Week 28: Operations handover complete
Deliverables¶
- Day-2 operations runbooks
- Troubleshooting guides
- Performance tuning procedures
- Team training materials
Sub-Project 2: Use-Cases Implementation Project¶
Phase 1: Study Phase (Weeks 15-18)¶
Duration: 4 weeks
Effort: 2-3 FTEs
Dependency: Infrastructure Design Phase 75% complete
Milestones¶
- Week 16: Use-case requirements gathered
- Week 17: Business value assessment completed
- Week 18: Use-case prioritization finalized
Deliverables¶
- Use-case requirements specification
- Business value assessment
- Implementation priority matrix
- Resource allocation plan
Phase 2: Design Phase (Weeks 19-26)¶
Duration: 8 weeks
Effort: 3-4 FTEs
Milestones¶
- Week 21: VM lifecycle use-cases designed
- Week 23: Application deployment patterns defined
- Week 25: Enterprise integration patterns completed
- Week 26: All use-case designs approved
Deliverables¶
- Use-case HLD and LLD documents
- Integration architecture designs
- Security and compliance frameworks
- Performance and scalability specifications
Phase 3: Implementation Phase (Weeks 27-38)¶
Duration: 12 weeks
Effort: 4-6 FTEs
Dependency: Infrastructure Implementation 80% complete
Milestones¶
- Week 29: VM lifecycle use-cases implemented
- Week 32: Hybrid applications deployed
- Week 35: Database services operational
- Week 37: Security and observability complete
- Week 38: All use-cases integrated
Deliverables¶
- Implemented use-cases with working demonstrations
- Configuration manifests and scripts
- Integration patterns and templates
- Security controls and policies
Phase 4: Testing Phase (Weeks 39-42)¶
Duration: 4 weeks
Effort: 3-4 FTEs
Milestones¶
- Week 40: Functional testing completed
- Week 41: Integration testing finished
- Week 42: Business validation approved
Deliverables¶
- Test execution reports
- Performance validation results
- Business outcome measurements
- User acceptance documentation
Phase 5: Day-2 Operations (Weeks 43-46)¶
Duration: 4 weeks
Effort: 2-3 FTEs
Milestones¶
- Week 44: Use-case runbooks completed
- Week 45: Monitoring dashboards operational
- Week 46: Knowledge transfer complete
Deliverables¶
- Use-case operational runbooks
- Monitoring and alerting configurations
- Best practices documentation
- Training materials
Sub-Project 3: Migration Workload from VMware Project¶
Phase 1: Study Phase (Weeks 21-28)¶
Duration: 8 weeks
Effort: 3-4 FTEs
Dependency: Infrastructure Implementation 60% complete
Milestones¶
- Week 23: VMware inventory completed
- Week 25: Workload assessment finished
- Week 27: Migration strategy approved
- Week 28: Migration waves defined
Deliverables¶
- Complete VMware workload inventory
- Workload assessment and compatibility analysis
- Migration strategy document
- Migration wave planning
- Risk assessment and mitigation plan
Phase 2: Design Phase (Weeks 29-36)¶
Duration: 8 weeks
Effort: 4-5 FTEs
Milestones¶
- Week 31: Migration architecture designed
- Week 33: VM templates standardized
- Week 35: Migration procedures documented
- Week 36: Pilot migration plan approved
Deliverables¶
- Migration architecture design
- VM template standards and configurations
- Migration procedure documentation
- Rollback and recovery procedures
- Pilot migration plan
Phase 3: Implementation Phase (Weeks 37-50)¶
Duration: 14 weeks
Effort: 5-7 FTEs
Dependency: Infrastructure Testing 100% complete
Milestones¶
- Week 39: Pilot migration completed
- Week 42: Wave 1 migrations finished
- Week 46: Wave 2 migrations completed
- Week 49: Wave 3 migrations finished
- Week 50: All critical workloads migrated
Deliverables¶
- Migrated virtual machines and applications
- Updated VM templates and configurations
- Migration execution reports
- Performance optimization results
- Updated network and security configurations
Phase 4: Testing Phase (Weeks 51-54)¶
Duration: 4 weeks
Effort: 4-5 FTEs
Milestones¶
- Week 52: Application functionality validated
- Week 53: Performance benchmarks achieved
- Week 54: Business continuity confirmed
Deliverables¶
- Application validation reports
- Performance comparison analysis
- Business continuity test results
- User acceptance confirmation
Phase 5: Day-2 Operations (Weeks 55-60)¶
Duration: 6 weeks
Effort: 3-4 FTEs
Milestones¶
- Week 57: Migration runbooks completed
- Week 58: Legacy decommissioning planned
- Week 60: Operations transition complete
Deliverables¶
- Migration operations runbooks
- Legacy infrastructure decommissioning plan
- Post-migration monitoring procedures
- Lessons learned documentation
Resource Planning¶
Team Composition by Sub-Project¶
Infrastructure Project¶
- Infrastructure Architect: 1 FTE
- DevOps Engineers: 2 FTEs
- System Administrators: 2 FTEs
- Security Engineer: 1 FTE
- Network Engineer: 1 FTE
Use-Cases Implementation¶
- Solution Architect: 1 FTE
- Application Developers: 3 FTEs
- Testing Specialist: 1 FTE
- DevOps Engineer: 1 FTE
- Security Specialist: 1 FTE
- Business Analyst: 1 FTE
Migration Project¶
- Migration Specialist: 1 FTE
- VMware Administrators: 2 FTEs
- RH OVE Engineers: 2 FTEs
- Application Owners: 2 FTEs
- Performance Engineer: 1 FTE
- Backup Administrator: 1 FTE
Cross-Project Coordination¶
Weekly Sync Meetings¶
- Architecture review board
- Technical coordination committee
- Risk and issue management
- Resource allocation review
Monthly Steering Committee¶
- Progress against milestones
- Budget and resource adjustments
- Risk escalation and mitigation
- Stakeholder communication
Risk Management¶
High-Risk Areas¶
- Resource Availability: Specialized skills in RH OVE and VMware
- Technical Complexity: Multi-cluster networking and storage
- Business Continuity: Migration impact on critical workloads
- Timeline Dependencies: Sequential phases with limited parallel execution
Mitigation Strategies¶
- Cross-training: Develop skills across multiple team members
- Proof of Concepts: Validate technical approaches early
- Phased Migration: Minimize business impact through careful wave planning
- Buffer Time: Include 15-20% contingency in timeline estimates
Success Metrics¶
Infrastructure Project¶
- 99.9% infrastructure uptime SLA
- Security compliance audit pass rate: 100%
- Performance benchmarks met or exceeded
- Team satisfaction with operational procedures
Use-Cases Project¶
- All documented use-cases successfully demonstrated
- Business value metrics achieved
- User adoption rates meet targets
- Documentation completeness and accuracy
Migration Project¶
- 100% critical workload migration success
- Performance parity or improvement: 95% of workloads
- Business continuity maintained throughout migration
- Legacy infrastructure decommissioning completed on schedule