RH OVE Ecosystem Risk Register

Document Information

  • Document Version: 1.0
  • Last Updated: TBD
  • Risk Assessment Period: Project Duration (12-18 months)

Risk Assessment Scale

Probability Scale

  • 1 - Very Low (0-10%): Risk unlikely to occur
  • 2 - Low (11-30%): Risk may occur in exceptional circumstances
  • 3 - Medium (31-50%): Risk may occur under certain conditions
  • 4 - High (51-80%): Risk likely to occur in most circumstances
  • 5 - Very High (81-100%): Risk almost certain to occur

Impact Scale

  • 1 - Very Low: Minimal impact on project objectives
  • 2 - Low: Minor impact with easy workarounds
  • 3 - Medium: Moderate impact requiring management attention
  • 4 - High: Major impact requiring significant resources
  • 5 - Very High: Critical impact threatening project success

Risk Score = Probability × Impact


Infrastructure Project Risks

Risk ID Risk Description Category Probability Impact Risk Score Owner Mitigation Strategy Status
INF-001 Resource contention with 2,000 VMs and 200 applications exceeding cluster capacity Technical 3 4 12 Infrastructure Architect Implement auto-scaling, capacity monitoring, and multi-cluster load balancing Open
INF-002 Network bottlenecks during peak usage with 40 Gbps requirement Technical 3 4 12 Network Engineer Design redundant network paths, implement QoS policies, traffic shaping Open
INF-003 Storage IOPS degradation with 200,000 IOPS requirement Technical 3 3 9 System Administrator Implement tiered storage, SSD caching, performance monitoring Open
INF-004 Cilium CNI configuration complexity in multi-cluster setup Technical 4 3 12 DevOps Engineer PoC validation, expert consultation, phased rollout Open
INF-005 Security vulnerabilities in multi-tenant environment Security 2 5 10 Security Engineer Regular security audits, penetration testing, network segmentation Open
INF-006 GitOps pipeline failures affecting deployment automation Operational 3 3 9 DevOps Engineer Implement pipeline monitoring, rollback procedures, backup deployment methods Open
INF-007 Backup system (Rubrik) integration issues with large dataset (1 PB) Technical 3 4 12 System Administrator Extensive testing, vendor support engagement, backup strategy validation Open
INF-008 Skills gap in RH OVE administration and troubleshooting Resource 4 3 12 Project Manager Training programs, knowledge transfer sessions, external consultant support Open
INF-009 Hardware procurement delays affecting project timeline External 3 4 12 Infrastructure Architect Early procurement planning, multiple vendor options, buffer time Open
INF-010 Monitoring system (Prometheus/Grafana) overload with 2,200 workloads Technical 3 3 9 System Administrator Distributed monitoring architecture, metric sampling, alert optimization Open

Use-Cases Implementation Risks

Risk ID Risk Description Category Probability Impact Risk Score Owner Mitigation Strategy Status
UC-001 Application compatibility issues with RH OVE platform (200 hybrid apps) Technical 3 4 12 Solution Architect Compatibility assessment, application inventory, testing framework Open
UC-002 Performance degradation in hybrid workload scenarios Technical 3 3 9 Performance Engineer Performance benchmarking, optimization guidelines, monitoring dashboards Open
UC-003 Integration complexity between containers, PaaS, and VMs Technical 4 3 12 Solution Architect Integration patterns, service mesh implementation, API gateway setup Open
UC-004 Business stakeholder availability for use-case validation Business 3 3 9 Business Analyst Early stakeholder engagement, flexible scheduling, clear communication plan Open
UC-005 Use-case dependencies causing implementation delays Operational 3 3 9 Project Manager Dependency mapping, parallel development tracks, modular implementation Open
UC-006 Security compliance requirements for PaaS services Security 2 4 8 Security Specialist Compliance framework development, security controls validation, audit preparation Open
UC-007 Data consistency issues in hybrid application scenarios Technical 2 4 8 Application Developer Data architecture design, consistency protocols, transaction management Open
UC-008 Observability gaps in complex multi-tier applications Operational 3 3 9 DevOps Engineer Distributed tracing implementation, log aggregation, custom metrics Open

Migration Project Risks

Risk ID Risk Description Category Probability Impact Risk Score Owner Mitigation Strategy Status
MIG-001 Data loss during migration of 500 TB across 1,000 VMs Technical 2 5 10 Migration Specialist Multiple backup strategies, checksum validation, pilot testing Open
MIG-002 Extended downtime exceeding 2-hour window per application Business 3 4 12 Migration Specialist Rehearsal migrations, optimized procedures, rollback planning Open
MIG-003 VMware licensing and dependency issues during transition Legal/Technical 3 3 9 VMware Administrator License audit, dependency mapping, phased decommissioning Open
MIG-004 Application performance degradation post-migration Technical 3 4 12 Performance Engineer Performance baselines, optimization procedures, monitoring setup Open
MIG-005 Network connectivity issues during migration waves Technical 3 3 9 Network Engineer Network planning, connectivity testing, backup communication paths Open
MIG-006 Resource contention during concurrent migrations (200 VMs per wave) Technical 4 3 12 RH OVE Engineer Resource planning, migration scheduling, capacity monitoring Open
MIG-007 Legacy application compatibility with new infrastructure Technical 4 4 16 Application Owner Compatibility testing, application modernization planning, fallback options Open
MIG-008 Staff resistance to new platform and procedures Change Management 3 3 9 Project Manager Change management program, training, communication strategy Open
MIG-009 Rollback complexity if migration fails Operational 2 4 8 Migration Specialist Detailed rollback procedures, automated rollback tools, testing protocols Open
MIG-010 Compliance and audit trail maintenance during migration Regulatory 2 4 8 Backup Administrator Audit procedures, compliance documentation, regulatory liaison Open

Cross-Project Risks

Risk ID Risk Description Category Probability Impact Risk Score Owner Mitigation Strategy Status
CP-001 Resource conflicts between concurrent sub-projects Resource 4 3 12 Project Manager Resource allocation matrix, coordination meetings, escalation procedures Open
CP-002 Timeline dependencies causing cascading delays Schedule 3 4 12 Project Manager Buffer time allocation, parallel execution planning, milestone monitoring Open
CP-003 Technical debt accumulation due to rapid deployment Technical 3 3 9 Technical Architect Code reviews, refactoring cycles, technical debt tracking Open
CP-004 Budget overruns due to scope creep and complexity Financial 3 4 12 Project Manager Budget monitoring, change control process, stakeholder communication Open
CP-005 Knowledge silos limiting cross-team collaboration Organizational 3 3 9 Project Manager Knowledge sharing sessions, documentation standards, cross-training Open
CP-006 Vendor support availability for critical issues External 2 4 8 Project Manager SLA agreements, escalation procedures, alternative support channels Open

Risk Monitoring and Review

Weekly Risk Review

  • Frequency: Every Tuesday during project execution
  • Attendees: Risk owners, project managers, technical leads
  • Agenda: New risks, status updates, mitigation progress

Monthly Risk Assessment

  • Frequency: First Friday of each month
  • Attendees: Steering committee, project sponsors
  • Agenda: Risk trend analysis, escalation decisions, resource adjustments

Risk Escalation Criteria

  • Immediate Escalation: Risk score ≥ 15 (High probability + High impact)
  • Weekly Escalation: Risk score ≥ 12
  • Monthly Review: Risk score ≥ 9

Risk Response Strategies

High-Priority Risks (Score ≥ 12)

  1. MIG-007: Legacy application compatibility - Requires immediate compatibility assessment
  2. CP-002: Timeline dependencies - Needs buffer time implementation
  3. INF-001: Resource contention - Auto-scaling implementation priority
  4. MIG-002: Extended downtime - Rehearsal migration mandatory

Medium-Priority Risks (Score 9-11)

  • Regular monitoring and mitigation progress tracking
  • Monthly review of mitigation effectiveness
  • Proactive communication with stakeholders

Low-Priority Risks (Score ≤ 8)

  • Quarterly review and assessment
  • Documentation of lessons learned
  • Contingency planning development

Success Metrics for Risk Management

Target KPIs

  • Risk Closure Rate: >80% of identified risks mitigated by project completion
  • Schedule Impact: <5% schedule variance due to risk materialization
  • Budget Impact: <10% budget variance due to risk management costs
  • Quality Impact: Zero critical system failures due to unmanaged risks

Risk Management Effectiveness

  • Early identification of 90% of project risks
  • Successful mitigation of all high-priority risks
  • No project-threatening risks materialized
  • Stakeholder satisfaction with risk communication and management