Weekly Workload Breakdown by Persona and Project
Overview
This document provides a detailed weekly workload breakdown in person-days for all personas across the three sub-projects of the RH OVE Ecosystem implementation.
Project Duration : 60 weeks (15 months)
Total Estimated Workload : 2,694 person-days
Persona Skill Levels and Availability
Persona Type
Skill Level
Standard Days/Week
Notes
Infrastructure Architect
Senior
5
Part-time (2.5 days) during Implementation
Solution Architect
Senior
5
Full-time during active phases
Migration Specialist
Senior
5
Full-time throughout migration project
DevOps Engineer
Mid-Senior
5
Multiple resources (2x)
Security Engineer
Senior
5
Full-time during active phases
Network Engineer
Senior
5
Full-time during active phases
Security Specialist
Senior
5
Full-time during active phases
Application Owner
Mid-Senior
5
Multiple resources (2x)
Performance Engineer
Mid-Senior
5
Full-time during active phases
Business Analyst
Mid-Senior
5
Full-time during active phases
RH OVE Engineer
Mid-Senior
5
Multiple resources (2x)
Application Developer
Mid-Level
5
Multiple resources (3x)
System Administrator
Mid-Level
5
Multiple resources (2x)
Testing Specialist
Mid-Level
5
Full-time during active phases
VMware Administrator
Mid-Level
5
Multiple resources (2x)
Backup Administrator
Mid-Level
5
Full-time during active phases
Project 1: RH OVE Infrastructure
Weekly Allocation by Phase (Person-Days)
Week
Phase
Infrastructure Architect
DevOps Engineer (2x)
System Administrator (2x)
Security Engineer
Network Engineer
Weekly Total (Days)
1-4
Study
5
0
0
0
5
10
5-12
Design
5
10
0
5
5
25
13-20
Implementation
2.5 (PT)
10
10
5
5
32.5
21-24
Testing
0
10
10
5
0
25
25-28
Day-2 Ops
0
10
10
0
0
20
Infrastructure Project Total: 582.5 person-days
Phase-wise Workload Summary
Study Phase (Weeks 1-4) : 40 person-days
Design Phase (Weeks 5-12) : 200 person-days
Implementation Phase (Weeks 13-20) : 260 person-days
Testing Phase (Weeks 21-24) : 100 person-days
Day-2 Operations (Weeks 25-28) : 80 person-days
Project 2: Use-Cases Implementation
Weekly Allocation by Phase (Person-Days)
Week
Phase
Solution Architect
Application Developer (3x)
Testing Specialist
DevOps Engineer
Security Specialist
Business Analyst
Weekly Total (Days)
15-18
Study
5
0
0
0
0
5
10
19-26
Design
5
0
0
0
5
5
15
27-38
Implementation
0
15
0
5
5
0
25
39-42
Testing
0
15
5
5
5
0
30
43-46
Day-2 Ops
0
0
0
5
0
0
5
Use-Cases Project Total: 560 person-days
Phase-wise Workload Summary
Study Phase (Weeks 15-18) : 40 person-days
Design Phase (Weeks 19-26) : 120 person-days
Implementation Phase (Weeks 27-38) : 300 person-days
Testing Phase (Weeks 39-42) : 120 person-days
Day-2 Operations (Weeks 43-46) : 20 person-days
Project 3: Migration from VMware
Weekly Allocation by Phase (Person-Days)
Week
Phase
Migration Specialist
VMware Admin (2x)
RH OVE Engineer (2x)
Application Owner (2x)
Performance Engineer
Backup Administrator
Weekly Total (Days)
21-28
Study
5
10
0
0
0
0
15
29-36
Design
5
10
0
10
0
0
25
37-50
Implementation
5
10
10
10
5
5
45
51-54
Testing
5
0
10
10
5
5
35
55-60
Day-2 Ops
5
0
10
0
5
5
25
Migration Project Total: 869 person-days
Phase-wise Workload Summary
Study Phase (Weeks 21-28) : 120 person-days
Design Phase (Weeks 29-36) : 200 person-days
Implementation Phase (Weeks 37-50) : 630 person-days
Testing Phase (Weeks 51-54) : 140 person-days
Day-2 Operations (Weeks 55-60) : 150 person-days
Summary by Sub-Project
Sub-Project
Duration (Weeks)
Total Workload (Person-Days)
Average Weekly Workload (Days)
RH OVE Infrastructure
28
582.5
20.8
Use-Cases Implementation
32
560
17.5
Migration from VMware
40
869
21.7
Total
60
2,011.5
33.5
Peak Resource Utilization
Highest Workload Weeks
Week Range
Projects Active
Weekly Workload (Days)
Key Activities
37-42
Infrastructure + Use-Cases + Migration
102.5
Implementation overlap
43-46
Use-Cases + Migration
30
Testing phases
47-50
Migration Implementation
45
Critical migration waves
Resource Overlap Analysis
Weeks 15-28 : Infrastructure and Use-Cases overlap
Weeks 21-46 : All three projects active simultaneously
Weeks 47-60 : Migration project completion phase
Workload Distribution by Persona Type
Persona Type
Total Weeks Active
Total Workload (Days)
Percentage
Migration Specialist
40
200
9.9%
Application Developer (3x)
16
240
11.9%
RH OVE Engineer (2x)
24
240
11.9%
VMware Administrator (2x)
28
280
13.9%
DevOps Engineer (2x)
36
360
17.9%
Infrastructure Architect
18.5
92.5
4.6%
System Administrator (2x)
16
160
8.0%
Security Engineer
16
80
4.0%
Network Engineer
20
100
5.0%
Solution Architect
12
60
3.0%
Testing Specialist
4
20
1.0%
Security Specialist
12
60
3.0%
Business Analyst
4
20
1.0%
Application Owner (2x)
26
260
12.9%
Performance Engineer
18
90
4.5%
Backup Administrator
30
150
7.5%
Notes
Part-time allocation : Infrastructure Architect works part-time (2.5 days/week) during Implementation phase
Resource multiplication : Numbers in parentheses (e.g., 2x, 3x) indicate multiple resources of the same type
Phase overlap : Some personas work across multiple phases with varying intensity
Workload estimates : Based on standard 5-day work weeks for full-time resources
Flexibility : Resource allocation can be adjusted based on project needs and availability
Risk Factors Affecting Workload
Skill scarcity : Specialized RH OVE and migration expertise may require extended timelines
Timeline compression : Accelerated delivery may require additional parallel resources
Scope changes : Additional use-cases or migration complexity could increase workload
Resource availability : Team member availability and scheduling conflicts may impact timelines
Learning curve : New team members may require additional time for technology familiarization
August 4, 2025